White Church Secondary Plan – Water, Wastewater and Stormwater Master Servicing Plan · Subdivision · 2023-12-01
Each category awards a maximum percentage of the annual stormwater charge as credit. Evidence is extracted directly from the source PDF — no manual review.
| Storm event | Pre-dev (m3/s) | Post-dev (m3/s) | Δ |
|---|---|---|---|
| 2-yr | — | — | — |
| 5-yr | — | — | — |
| 25-yr | — | — | — |
| 100-yr | — | — | — |
Outlets to 1200mm dia. open bottom concrete culvert; pre-development catchment 101 (17.87 ha); target release rates: 2yr=0.143 m3/s, 5yr=0.264 m3/s, 25yr=0.472 m3/s, 100yr=0.656 m3/s
Outlets to 1000mm dia. culvert; pre-development catchment 102 (32.00 ha); target release rates: 2yr=0.212 m3/s, 5yr=0.406 m3/s, 25yr=0.750 m3/s, 100yr=1.065 m3/s
Outlets to 900mm dia. culvert; pre-development catchment 104 (57.94 ha); target release rates: 2yr=0.430 m3/s, 5yr=0.796 m3/s, 25yr=1.428 m3/s, 100yr=1.995 m3/s
Located south of White Church Road within Greenbelt lands; outlets to drainage feature south of White Church Road; pre-development catchments 107, 108 (21.38 ha total); target release rates: 2yr=0.169 m3/s, 5yr=0.311 m3/s, 25yr=0.562 m3/s, 100yr=0.788 m3/s
Outlets to twin 600mm dia. culverts; pre-development catchment 109 (23.26 ha); target release rates: 2yr=0.164 m3/s, 5yr=0.305 m3/s, 25yr=0.551 m3/s, 100yr=0.772 m3/s
Outlets to 600mm dia. culvert; pre-development catchment 116 (41.78 ha); target release rates: 2yr=0.288 m3/s, 5yr=0.537 m3/s, 25yr=0.972 m3/s, 100yr=1.365 m3/s
Outlets to 800mm dia. culvert; pre-development catchment 118 (63.51 ha); target release rates: 2yr=0.441 m3/s, 5yr=0.815 m3/s, 25yr=1.466 m3/s, 100yr=2.052 m3/s
Catchment 207 is approximately 3.3 ha; too small for a SWM pond; outlets to existing drainage feature and Upper James Street culverts
On-site controls for panhandle area; outlets to existing drainage feature flowing west to east
How to read this page. Every value above was extracted from the source PDF by the PARCELFLOW report parser, which combines a layout-robust template detector with a validated extraction stage tuned to Ontario Functional Servicing and Stormwater Management reports. The four-category scorecard maps the parsed evidence onto Mississauga's credit bylaw. Numbers are estimates — engineering review still required before submitting a formal credit application to the City.