Parsed SWM report

Upper Wellington Street

Upper Wellington Street (Limeridge Road East to Stone Church Road East) Schedule C (Phases 1–4) Municipal Class Environmental Assessment · Retrofit · 2025-06-27

Consultant: WSP Canada Inc. / WSP E&I Canada Limited Model: PCSWMM Revision: Final
Credit scorecard — Hamilton bylaw

Each category awards a maximum percentage of the annual stormwater charge as credit. Evidence is extracted directly from the source PDF — no manual review.

On-site controls
documented source control on the site
50%
Lake Ontario green-space bonus
direct discharge + green-space parcel flag (90% tier) — not documented
0%
Net credit
50% baseline; up to 90% with Lake Ontario direct-discharge + green-space flag
50%
Pre vs post peak discharge
Storm eventPre-dev (m3/s)Post-dev (m3/s)Δ
5-yr 24-hr2.7
100-yr 24-hr4.89
Stormwater controls (6)
Underground storageSuperpipe System – Sirente Drive

Conceptual superpipe storage system proposed for quantity control at Sirente Drive; sized to control post-development peak flows to existing conditions for 2- through 100-year storms

Underground storageSuperpipe System – Desoto Drive

Conceptual superpipe storage system proposed for quantity control at Desoto Drive; sized to control post-development peak flows to existing conditions for 2- through 100-year storms

InfiltrationInfiltration Trenches / Infiltrative BMPs
Outletoverflow

Infiltration trenches proposed under pedestrian/bike lanes and sidewalks for erosion/volume control (25 mm event) and water quality; 50 mm clear stone with 0.4 void ratio; minimum 1 m above groundwater/bedrock; subject to geotechnical confirmation

OtherTree Planter/Soil Retention Cells
Outletoverflow

Silva Cells or equivalent modular cellular soil storage systems carried forward for consideration; provide infiltration and evapotranspiration; require pre-treatment (CB Shields or OGS)

Oil-grit separatorOil/Grit Separator Units (OGS)

Two OGS units proposed downstream of superpipe systems for quality control; City accepts 50% TSS removal credit for OGS; Stormceptor EF or equivalent; secondary controls (CB Shields) also anticipated south of Desoto Drive

OtherCB Shield Inserts

CB Shield catch basin inserts proposed as secondary water quality measure particularly south of Desoto Drive to Stone Church Road East; up to 50% TSS removal per ETV testing

Best management practices (9)
Infiltration TrenchesTree Planter/Soil Retention Cells (Silva Cells)Oil/Grit Separators (OGS)CB Shield InsertsExfiltration PipesPermeable Pavers/PavementEnhanced Grassed Swales (screened out)Filter Strips (screened out)Bioretention Systems (screened out)
Site characteristics & report metadata
ProjectUpper Wellington Street (Limeridge Road East to Stone Church Road East) Schedule C (Phases 1–4) Municipal Class Environmental Assessment
Project typeRetrofit
DeveloperCity of Hamilton
Existing land useroadway / urban right-of-way
Proposed land useroadway / urban right-of-way (widened/reconfigured)
Water balance capture25.0 mm
TSS removal target80%
Quality control methodOil/grit separator units downstream of underground storage superpipes, CB Shield catch basin inserts as secondary treatment, infiltration trenches and tree planter/soil retention cells as LID BMPs; 80% TSS removal required for new impervious area
Extraction audit
Confidence: medium Completeness: 67% Source: 89-page PDF Extractor: PARCELFLOW v1 Validation: review recommended

How to read this page. Every value above was extracted from the source PDF by the PARCELFLOW report parser, which combines a layout-robust template detector with a validated extraction stage tuned to Ontario Functional Servicing and Stormwater Management reports. The four-category scorecard maps the parsed evidence onto Mississauga's credit bylaw. Numbers are estimates — engineering review still required before submitting a formal credit application to the City.