Credit scorecard — Mississauga bylaw
Each category awards a maximum percentage of the annual stormwater charge as credit.
Evidence is extracted directly from the source PDF — no manual review.
✓Peak Flow
only some design storms documented
40%
✓Water Quality
TSS removal 85% (enhanced)
30%
✓Runoff Volume
water balance retains 5 mm on site (2% per mm, max 30% at 15 mm)
30%
✓Operations
BMPs + P.Eng present; sub-credit detection pending — full 20% requires explicit O&A items
20%
Net credit
Capped at 50% of annual stormwater charge
50%
Pre vs post peak discharge
| Storm event | Pre-dev (m3/s) | Post-dev (m3/s) | Δ |
| 10-yr | 0.123 | 0.122 | −1% |
Stormwater controls (4)
Oil-grit separatorOGS 1 (Stormceptor EFO4)
Stormceptor EFO4, drainage area 0.512 ha, 85% TSS removal efficiency, upstream flow control orifice flow rate 95 L/s, located upstream of storage tank in parking garage
Underground storageStorage Tank
Storage volume92.0 m³
Outletpipe
Located in southwest corner of site at P1 level of underground parkade; likely requires pump to discharge to 450mm concrete storm sewer on Elizabeth Street South via 300mm connection to EX. MH 1; controls 0.512 ha of site area
Green roofGreen Roof
Approximately 526 m2 of green roof incorporated on roofs of proposed building; provides flow attenuation, filtration, and evapotranspiration
Rainwater harvesting / reuseRainwater Harvesting - Irrigation and Mechanical
Rainwater collected in sump of storage tank used for irrigation of landscaped areas and planters; excess used for mechanical re-use
Best management practices (6)
Oil-Grit Separator (Stormceptor EFO4)Underground storage tankGreen roofLandscaped areas (planting media above parking garage and planting boxes)Rainwater harvesting for irrigationRainwater harvesting for mechanical uses
Site characteristics & report metadata
Project42 Port Street East & 91-93, 99 Lakeshore Road East
Project typeRedevelopment
DeveloperCentre City Capital Ltd., FRAM + Slokker, Kilmer Group
Existing land usecommercial with surface parking and a heritage home
Proposed land useresidential condominium and commercial (11-storey, 221 unit)
Site area0.58 ha
Water balance capture5.0 mm
TSS removal target85%
Quality control methodoil-grit separator (Stormceptor EFO4) upstream of underground storage tank
Extraction audit
Confidence: high
Completeness: 83%
Source: 57-page PDF
Extractor: PARCELFLOW v1
Validation: passed
Source PDF: Functional-Servicing-and-Stormwater-Management-Report-OZ-OPA-22-30-W.pdf (57 pages)
Open source PDF →
Starter package
Download credit application package »
10-page PDF: pre-filled Form 2703, starter P.Eng report skeleton, submission checklist. Engineer reviews, adds site inspection + O&M plan, certifies + submits.
Download PDF »
How to read this page. Every value above was extracted from the source PDF by the
PARCELFLOW report parser, which combines a layout-robust template detector with a
validated extraction stage tuned to Ontario Functional Servicing and Stormwater
Management reports. The four-category scorecard maps the parsed evidence onto
Mississauga's credit bylaw. Numbers are estimates — engineering review still required
before submitting a formal credit application to the City.