Parsed SWM report

3855-3915 Dundas Street West

3855-3915 Dundas Street West Mixed Industrial, Commercial, and Self-Storage Development · New · 2023-09-27

Consultant: C.F. Crozier & Associates Inc. Engineer: Andrew Farina, P.Eng. P.Eng sealed Model: UNKNOWN Revision: Rev 2
Credit scorecard — Mississauga bylaw

Each category awards a maximum percentage of the annual stormwater charge as credit. Evidence is extracted directly from the source PDF — no manual review.

Peak Flow
pre-vs-post controlled across multiple storms; avg reduction 62%
40%
Water Quality
TSS removal 80% (enhanced)
30%
Runoff Volume
water balance retains 5 mm on site (2% per mm, max 30% at 15 mm)
30%
Operations
BMPs + P.Eng present; sub-credit detection pending — full 20% requires explicit O&A items
20%
Net credit
Capped at 50% of annual stormwater charge
50%
Pre vs post peak discharge
Storm eventPre-dev (L/s)Post-dev (L/s)Δ
2-yr99.3544.32−55%
5-yr128.9854.21−58%
10-yr158.8662.97−60%
25-yr200.772.82−64%
50-yr244.484.4−65%
100-yr291.7394.72−68%
Stormwater controls (3)
Underground storageCupolex Underground Concrete Storage Tank
Storage volume856.3 m³
Outletorifice
Outlet invert167.71 m
100-yr HGL169.51 m

125 mm orifice tube; Cupolex Rialto H.1800 mm forming system; inside tank area 513 m2; system depth 1800 mm; controls 100-yr post-development flow to 2-yr pre-development flow rate

InfiltrationPermeable Pavers (Ecoraster)
Storage volume129.8 m³
Surface area0.130 ha
Outletother

1298 m2 area; 250 mm bedding depth; 0.4 void ratio clear stone; provides water balance retention volume of 129.8 m3 against requirement of 117.9 m3

OtherUp-Flo Filtration System
Outletother

Up-Flow filtration system downstream of underground chamber; provides 80% TSS removal (MOECP Enhanced Level of Protection)

Best management practices (4)
Cupolex Underground Concrete Storage TankUp-Flo Filtration SystemPermeable Pavers (Ecoraster)125 mm Orifice Tube
Site characteristics & report metadata
Project3855-3915 Dundas Street West Mixed Industrial, Commercial, and Self-Storage Development
Project typeNew
DeveloperDymon Group of Companies
Existing land usevacant
Proposed land usemixed industrial, commercial, and self-storage
Site area2.39 ha
Impervious0% (pre) → 58% (post)
Water balance capture5.0 mm
TSS removal target80%
Allowable release rate99.3 L/s
Quality control methodUp-Flo filtration system (up-flow filter) downstream of underground detention tank providing 80% TSS removal
Extraction audit
Confidence: high Completeness: 100% Source: 59-page PDF Extractor: PARCELFLOW v1 Validation: passed
Source PDF: Functional-Servicing-and-Stormwater-Management-Report-October-2023.pdf (59 pages) Open source PDF →
Starter package
Download credit application package »
10-page PDF: pre-filled Form 2703, starter P.Eng report skeleton, submission checklist. Engineer reviews, adds site inspection + O&M plan, certifies + submits.
Download PDF »

How to read this page. Every value above was extracted from the source PDF by the PARCELFLOW report parser, which combines a layout-robust template detector with a validated extraction stage tuned to Ontario Functional Servicing and Stormwater Management reports. The four-category scorecard maps the parsed evidence onto Mississauga's credit bylaw. Numbers are estimates — engineering review still required before submitting a formal credit application to the City.